Basic principles of paver spreading       

1, start paving work, should determine the minimum and maximum paving width, and set the response of paver.

2, paving work also need to work closely with other departments of the construction site, to ensure uninterrupted feeding and avoid feeding time consuming too much.

3, car should be arranged reasonably, avoid the paving process in stop and go.

4, 5, and the mixing station to keep in touch, to ensure that the planned supply.

6. Regularly check the use of paver, timely maintenance (such as check oil level, electrical and hydraulic function is normal, etc.).

7, car insulation tarpaulin should be removed before discharge, which can avoid the paving material temperature decrease.

8, try to maintain a constant speed of paver. If the feeding speed can not meet the normal paving speed, then keeping low speed continuous paving is far better than the high-speed multi interrupted paving effect.

9, a long time to work in middle temperature environment, your wise choice should use light paver paving material stored in all, and then raise the screed and clean. When a new feed, can lower the screed to work.

10, paving material consumption and temperature should be regularly detected.