What did you do before the hydraulic system was debugged?
Hydraulic equipment installation and debugging of hydraulic system of qualified flushing, the hydraulic system adjustment test is a necessary procedure, which is aimed at the premise to meet the technical parameters, make the necessary adjustments according to the actual requirements of the production process, under heavy load can run normally.
Preparation of hydraulic system before dispatching
The hydraulic system to be debugged must be qualified after circulating flushing, and then can enter the debugging state.
The hydraulic drive main equipment is all installed, and the moving parts are in good condition. After passing the inspection, they enter the debugging state.
Control the hydraulic system of electrical equipment and lines all installed and checked qualified.
Familiar with the required technical documents, such as hydraulic schematic diagram, piping installation diagram, system instructions, system commissioning instructions, etc.. According to the above technical documents, check whether the pipeline connection is correct and reliable, whether the selected oil meets the requirements of technical documents, whether the oil level in the tank reaches the required height, according to the schematic diagram, assembly diagram to identify the position of the hydraulic components.
Clear the sundries around the main engine and the hydraulic equipment, the debugging site should have obvious safety facilities and signs, and the special person is responsible for the management.
Participate in commissioning personnel should be clear division of labor, unified command, the necessary training for operators, if necessary, equipped with walkie talkie, convenient contact.