Construction of Hong Kong Zhuhai Macao Bridge with ZOOMLION QAY500 all terrain crane
Recently, zoomlio QAY500 crane power the world's longest cross sea bridge project - HZMB groundbreaking ceremony was held in Hong Kong Hong Kong Yuen, hoisting industry nearly 150 industry gathered to witness the mainland so far the largest export tonnage all terrain crane in port station. Mr. Xiong Yanming, vice president of ZOOMLION and general manager of overseas company, attended the ceremony.
ZOOMLION since 2008 to enter the Hongkong crane market, continue to maintain the leading position of local industry, the participation of the Hong Kong Zhuhai bridge QAY500 all terrain crane maximum lifting capacity of 500 tons, mainly responsible for the Artificial Island Bridge traffic hub project, lifting 60 tons to 120 tons of concrete components.
ZOOMLION project leader revealed that, due to the construction site adjacent to Hong Kong International Airport, airport ATC has strict requirements for electromagnetic interference, ZOOMLION combined with the project needs, the product has made special improvements, fully meet the project requirements and customer needs.
Data show that the HZMB project route from Hong Kong International Airport near Hongkong port artificial island, Tai O, across Lingdingyang waters, and finally into a Y shape, one end is connected with the Zhuhai Macao route, connected at one end, a total length of 55 km.
The Hong Kong Zhuhai Macao Bridge started in Zhuhai in December 15, 2009, the main bridge bridge in September this year officially opened, but the Hongkong project suffered downtime striking one snag after another, for a period of time, until 2011 Hongkong port artificial island was re started, other related ancillary facilities and supporting the construction of is wildly beating gongs and drums.
It is understood that although the Hongkong section of the project was delayed, but the government through the modification of construction methods, increase high-end equipment and other ways to improve efficiency, to ensure the completion of the Hongkong section as scheduled, with the bridge opened to traffic at the end of 2017. The ZOOMLION large tonnage full road crane power, will cooperate with changes in construction methods, to help the construction side compression project time, to ensure the completion of the project in Hongkong as scheduled.
The Hong Kong Zhuhai Macao Bridge is the largest cross sea transportation project for the first time in Guangdong, Hong Kong and Macao under the framework of "one country, two systems", which is the longest cross sea bridge project in the world, and it is also the three longest cross sea bridge project in the world. As the longest span, the most investment and the most difficult construction of the cross sea bridge project in China's construction history, the Hong Kong Zhuhai Macao Bridge has attracted wide attention at home and abroad.
The person in charge of the project said ZOOMLION, the Hong Kong Zhuhai Macao Bridge will link the world's most dynamic economic region, the completion of the bridge in Hongkong, Macao, Zhuhai three far-reaching economic and social integration, we are very proud to be the century project equipment supplier, in the formal construction next, ZOOMLION will be completed with high efficiency, excellent the performance of the bridge with high quality power."