High efficiency 8.5m in Liugong forklift truck struck

In November 2015, an emergency order to Liugong, needs 1 8.5m door frame CPC35A forklift, delivery time: 25 days. This is a special order for Liugong all started boiling, because this is not an ordinary order for Liugong some difficulty speaking, but at the same time, this is also the door frame of super forklift company challenges and opportunities.

Said the door frame forklift is a challenge is not exaggerated, the door frame is one of the important working device of forklift gantry, strength and deformation control, set up in the rising process of stability and security has always been the industry concern technical difficulties.

Facing the special order with high risk, high difficulty and short delivery time, Liugong forklift company convened the feasibility research of designers and sales personnel of industrial vehicle marketing company, and finally decided to take the arduous task.

Immediately, the company set up a PLM team led by the Institute, set up a procurement team, process quality, manufacturing and other project teams, and implemented and monitored all aspects of the project step by step, ensuring the orderly and efficient development of the project.

Standard portal frame height is generally only 3M. At present, Liugong, including domestic forklift manufacturers, has the highest design height of only 7m. Even though the leading industry of the industry, the highest gate height is only 8m.

In addition, the door frame design stage, R & D personnel personally to the construction site investigation using condition of customers, understand customer needs and focus on key projects, the quality of personnel, information and data process through each way to collect the feedback information and benchmarking, a failure model library, the use of computer systems for IE system analysis of main components, ensure the door frame structure reliability and stability.

In the manufacturing stage of portal frame, we should work closely with R & D, process, quality and production workshop staff, work overtime, identify problems, respond immediately, deal with them immediately, and ensure the smooth development of manufacturing process. In December 25th, the company has 8.5m high frame CPC35A forklift finally succeeded in the earth, and the successful completion of commissioning work.

In the door frame test stage, the test personnel of the forklift Institute carried out performance tests and stability tests on the vehicle. When the door frame 8.5m CPC35A forklift in various extreme conditions still stably docked in the stability test platform, site personnel are all proud and pride. In December 27th, the 8.5m in CPC35A forklift smooth delivery to the customer. As of the deadline, failure feedback from the customer is not received.

Accompanied by the beautiful 8.5m forklift door frame developed CPC35A completed, Liugong forklift technology and carry on a new level, is a milepost Liugong history, also marks the company in R & D, ultra shelf manufacturing technology to achieve domestic industry leading level.